The foundations of the Go Four It are being laid. Now that the reinforcement, lightning protection and foundation pipes have been installed, the first concrete has started to flow. Two M47 pumps and 22 truck mixers were used to pour the first of a total of eight base plate slab sections. The 5,700 square meter floor slab, up to one meter thick, for the Go Four Red and Go Four Purple buildings will be completed by July.
Many thanks to Leitner GmbH & Co. Bauunternehmung KG, which is building the shell of the Go Four It business quarter.